Timeline

Construction Header


This page provides a timeline for the Elementary Campus building and renovation projects. Some of these dates are subject to change and may be adjusted as the projects progress.



Timeline


June 2017 -
Elementary Campus Project authorization

June 2017 - May 2018 Design Development Phase
  • Sloan Renovations (Primary grades K-2)
  • New Intermediate School (grades 3-5)
August 2018 -
Murrysville Council hearing on proposed Sloan project

October 2018  -
Murrysville Council Approves Project


December 2018 -
Act 34 Hearing

January 2019 -
Board approves advertising for construction bids

February 2019 -
Bid Openings (for Renovation & New Construction)

March 2019 -
All bids rejected by Board

March 2019 -
Rebidding process for both projects authorized by Board




Future Projects:



High School Renovations & Additions - TBD         
  • Stadium Upgrades
  • Potential Community Health & Wellness Center
  • Athletic Fields
  • Campus Reorganization

 

Middle School Renovations - TBD